The Effluent & Wastewater Pipelines & SR89 Improvements Project is located between the Phippen Roundabout and the Willow Lake Road Roundabout. The project will increase pipeline capacity and centralize wastewater treatment to the Airport Water Reclamation Facility (AWRF) while simultaneously distributing effluent from the AWRF. The project will also include roadway and intersection safety improvements throughout the corridor.
Sign up to receive future updates.
Project Timeline
*Click the underlined text for links.
June 2023: City Council Study Session
June 2023 - November 2023: Public Survey Period
September/October 2023: Two Open House Community Meetings
December 2023: City Council Study Session
February 2024: Scoping Report Finalized
March 2024 - July 2024: Request for Statement of Qualifications
November 19, 2024: Award Engineering Design Services Contract
Spring 2025: City Council Study Session
Fall 2025: 15% Design/Design Concept Report Complete
Fall 2025: City Council Study Sessions/Public Hearings
Early 2026: Construction Manager at Risk Evaluation and Selection
Spring 2027: Final Design Plans Complete
Summer 2027: Begin Construction